The new car park has been built and we expect it to be opened soon.

The revised plan below shows the playground that will be built on the existing car park and extending into the Common. The new schedule for the other works planned is as below.

  • Works to playroom, play area and changing rooms adjacent to the adventure playground in the park are to start May 8th 2017 with completion 26th October 2017.
  • Construction of new playground on the old car park extending into the Common - start and completion dates as above.
  • Works to restore and return to the Common the area west of the cafe to start October 26th.